Highway 101 Marin-Sonoma Narrows (MSN) Project Segment A (modified) |
Description: In and near Novato, from Route 37 to Atherton Avenue - Widen 4-lane expressway to 6-lane freeway for HOV lanes. TCR #18
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Marin, Sonoma |
City | Novato |
Zip Code | 94945, 94947, 94949, 94952 |
Senate District |
03 |
Assembly District | 06 |
Congressional District | 06 |
Caltrans District |
04 |
County/State Route | Sonoma 101 |
Postmile Begin/End | 0 7.1 |
County/State Route | Marin 101 |
Postmile Begin/End | 18.6 27.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1200 | 2,384 |
Lane Miles Added (HOV) | 5.2 | 0 |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 106107 | 189,857 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Wajahat Nyaz | (510)286-5119 | wajahat.nyaz@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Wajahat Nyaz | (510)286-5119 | wajahat_nyaz@dot.ca.gov | |
Right of Way Phase |
Caltrans | Wajahat Nyaz | (510)286-5119 | wajahat.nyaz@dot.ca.gov | |
Construction Phase |
Caltrans | Wajahat Nyaz | (510)286-5119 | wajahat.nyaz@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Juliana Gum | (510)286-4579 | juliana.gum@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $10,450 | $10,450 | ||||
IIP Augmentation |
$0 | $6,800 | $6,800 | ||||
CMIA |
$82,400 | $96,946 | $179,346 | ||||
SLPP |
$0 | $1,865 | $1,865 | ||||
Non-bond Funding | |||||||
State/Federal* |
$93,800 | $-10,449 | $83,351 | ||||
Local** |
$26,599 | $18,011 | $44,610 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $202,799 | $123,623 | $326,422 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$22,800 | $3,067 | $25,867 | $4,247 | |||
Design(PS&E) |
$18,100 | $7,246 | $25,346 | $23,804 | |||
Right of Way |
$22,440 | $38,437 | $60,877 | $45,266 | |||
Construction |
$139,459 | $74,872 | $214,331 | $211,070 | |||
Total* | $202,799 | $123,623 | $326,422 | $284,388 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2001 10/30/2008 |
01/17/2019 01/17/2019 |
01/01/2001 09/30/2009 |
100 | 01/02/2001 10/29/2009 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2008 07/01/2010 |
01/17/2019 01/17/2019 |
09/30/2009 07/01/2010 |
100 | 10/30/2009 10/06/2010 |
-1 -3 |
|
Begin Right of Way Phase
End Right of Way Phase |
10/30/2008 07/01/2010 |
01/17/2019 01/17/2019 |
09/30/2009 07/01/2010 |
100 | 10/30/2009 07/01/2010 |
-1 0 |
|
Begin Construction Phase
End Construction Phase |
12/01/2010 12/02/2013 |
01/17/2019 01/17/2019 |
12/01/2010 12/02/2013 |
100 | 07/05/2011 12/12/2012 |
-7 12 |
|
Begin Closeout Phase
End Closeout Phase |
12/02/2013 12/02/2014 |
01/17/2019 01/17/2019 |
12/02/2013 12/02/2014 |
75 | 12/12/2012 08/23/2019 |
12 -57 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 09/01/2010 | 0 | 0 | ||||
Implementation Date | 09/01/2010 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1200 | 2,384 |
Lane Miles Added (HOV) | 5.2 | 0 |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 106107 | 189,857 |
Bond Funding Cost | |
---|---|
Adopted: |
$82,400,000 |
Current Approved: |
$72,717,000 |
Actual Expenditures: |
$72,368,000 |
Status as of December 31, 2023.