Highway 101 Marin-Sonoma Narrows (MSN) Project Segment A (modified)

Description: In and near Novato, from Route 37 to Atherton Avenue - Widen 4-lane expressway to 6-lane freeway for HOV lanes. TCR #18

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Marin, Sonoma
City Novato
Zip Code 94945, 94947, 94949, 94952
 
Senate District
03
Assembly District 06
Congressional District 06
 
Caltrans District
04
 
 
County/State Route Sonoma 101
Postmile Begin/End 0 7.1
 
County/State Route Marin 101
Postmile Begin/End 18.6 27.6
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1200    2,384  
Lane Miles Added (HOV)  5.2    0  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)  106107    189,857  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Wajahat Nyaz (510)286-5119   wajahat.nyaz@dot.ca.gov
Design (PS&E) Phase
Caltrans Wajahat Nyaz (510)286-5119   wajahat_nyaz@dot.ca.gov
Right of Way Phase
Caltrans Wajahat Nyaz (510)286-5119   wajahat.nyaz@dot.ca.gov
Construction Phase
Caltrans Wajahat Nyaz (510)286-5119   wajahat.nyaz@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510)286-4579   juliana.gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $10,450 $10,450
IIP Augmentation
$0 $6,800 $6,800
CMIA
$82,400 $96,946 $179,346
SLPP
$0 $1,865 $1,865
Non-bond Funding
State/Federal*
$93,800 $-10,449 $83,351
Local**
$26,599 $18,011 $44,610
Non Budgeted ETC
$0 $0 $0
 
Total**** $202,799 $123,623 $326,422

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$22,800 $3,067 $25,867 $4,247
Design(PS&E)
$18,100 $7,246 $25,346 $23,804
Right of Way
$22,440 $38,437 $60,877 $45,266
Construction
$139,459 $74,872 $214,331 $211,070
 
Total* $202,799 $123,623 $326,422 $284,388

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2001 

10/30/2008 
01/17/2019 

01/17/2019 
01/01/2001 

09/30/2009 
100  01/02/2001 

10/29/2009 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2008 

07/01/2010 
01/17/2019 

01/17/2019 
09/30/2009 

07/01/2010 
100  10/30/2009 

10/06/2010 
-1 

-3 
Begin Right of Way Phase

End Right of Way Phase
10/30/2008 

07/01/2010 
01/17/2019 

01/17/2019 
09/30/2009 

07/01/2010 
100  10/30/2009 

07/01/2010 
-1 

Begin Construction Phase

End Construction Phase
12/01/2010 

12/02/2013 
01/17/2019 

01/17/2019 
12/01/2010 

12/02/2013 
100  07/05/2011 

12/12/2012 
-7 

12 
Begin Closeout Phase

End Closeout Phase
12/02/2013 

12/02/2014 
01/17/2019 

01/17/2019 
12/02/2013 

12/02/2014 
75  12/12/2012 

08/23/2019 
12 

-57 
Corridor System Management Plan
Adoption Date     09/01/2010   
Implementation Date     09/01/2010   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1200 2,384
Lane Miles Added (HOV) 5.2 0
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 106107 189,857

Bond Funding Cost
Adopted:
$82,400,000
Current Approved:
$72,717,000
Actual Expenditures:
$72,368,000

 

Status as of December 31, 2023.